128 OF 148  CITY OF LACKAWANNA • NY 2026 ZONING ORDINANCE | Chapter 300: Zoning

  c. Foundation standards.  iii  Pile foundation analysis shall also
  include consideration of piles in
  i.  The pilings or column foundation
  column action from the bottom of the
  and structure attached thereto
  structure to the stable soil elevation
  shall be adequately anchored to
  of the site. Pilings may be horizontally
  resist flotation, collapse or lateral
  or diagonally braced to withstand
  movement due to the effects of
  wind and water forces.
  wind and water pressures acting
  simultaneously on all building  iv. The minimum acceptable sizes for
  components. Foundations must be  timber piles are a tip diameter of
  designed to transfer safely to the  eight inches for round timber piles
  underlying soil all loads due to wind,  and eight inches by eight inches for
  water, dead load, live load and other  square timber piles. All wood piles
  loads (including uplift due to wind  must be treated in accordance with
  and water).  requirements of EPEE-C3 to minimize
  decay and damage from fungus.
  ii.  Spread footings and fill material shall
  not be used for structural support  v.  Reinforced concrete piles shall be
  of a new building or substantial  cast of concrete having a twenty-
  improvement of an existing structure.  eight-day ultimate compressive
  strength of not less than 5,000
  d. Pile foundation design.  pounds per square inch, and shall
  i.  The design ratio of pile spacing to  be reinforced with a minimum of
  pile diameter shall not be less than  four longitudinal steel bars having
  8:1 for individual piles (this shall not  a combined area of not less than
  apply to pile clusters located below  1% nor more than 4% of the gross
  the design grade). The maximum  concrete area. Reinforcing for precast
  center-to-center spacing of wood  piles shall have a concrete cover of
  piles shall not be more than 12 feet  not less than 1 1/4 inches for No. 5
  on center under load-bearing sills,  bars and smaller and not less than
  beams, or girders.  1 1/2 inches for No. 6 through No. 11
  bars. Reinforcement for piles cast in
  ii.  Pilings shall have adequate soil
  the field shall have a concrete cover
  penetration (bearing capacity)
  of not less than two inches.
  to resist the combined wave and
  wind loads (lateral and uplift)  vi. Piles shall be driven by means of a
  associated with the base flood acting  pile driver or drop hammer, jetted, or
  simultaneously with typical structure  augered into place.
  (live and dead) loads, and shall  vii. Additional support for piles in the
  include consideration of decreased  form of bracing may include lateral or
  resistance capacity caused by  diagonal bracing between piles.
  erosion of soil strata surrounding the
  piles. The minimum penetration for
  foundation piles is to an elevation of
  five feet below mean sea level (msl)
  datum if the BFE is +10 msl or less, or
  to be at least 10 feet below msl if the
  BFE is greater than +10 msl.