TOWN OF HAMBURG
  6100 S. Park Ave
  Hamburg, NY 14075
  716-649-6111
  www.townofhamburgny.gov

  Schedule of Fees  January 1, 2027

MAJOR SUBDIVISON - PRIVATE
  Fees
WITH NO PUBLIC IMPROVEMENTS
Rezoning Application Fees  Planning Department Fees  Engineering Department Fees
1 Acre or less  $550  None
>1 - 5 Acres  $1,600  None
>5 - 10 Acres  $3,200  None
>10 - 50 Acres  $5,300  None
>50 Acres  $8,000  None

MINOR SUBDIVISION UP TO 4 LOTS  Planning Department Fees  Engineering Department Fees
Sketch Plan  $200  None
Preliminary Plan  $300 + $300/lot over 2  $200 (if required)
Public Hearing Fee  $350  None
Final Plat Map Cover (if required)  None  $350

MAJOR SUBDIVISION 5 LOTS OR MORE (no PIP)  Planning Department Fees  Engineering Department Fees
Sketch Plan  $750  $500
Preliminary Plan + $300/lot over 5  $1,500 + $300/lot over 5  $1,000 + $200/lot over 5
Public Hearing Fee  $350  $200
Final Plat Map Cover (if required)  None  $1,000
Re-review of subdivision materials  None  $1,500

MAJOR SUBDIVISION 5 LOTS OR MORE (with PIP)  Planning Department Fees  Engineering Department Fees
Sketch Plan  $750  $750
Preliminary Plan + $300/lot over 5  $2,000 + $300/lot over 5  $2,500 + $300/lot over 5
Public Hearing Fee  $415  $375
Final Plat Map Cover (if required)  None  $2,000
Re-review of subdivision materials  None  $2,000

All Subdivisions per # Lots/Units  Planning Department Fees  Engineering Department Fees
Final Engineering Review Fee  None  $70 per lot/unit up to 20
Final Engineering Review Fee  None  $50 per lot/unit over 20

Public Improvement Permit  Planning Department Fees  Engineering Department Fees
PIP Permits  None  Based on project costs
Clearing, Striping and Erosion Sediment Control  None  Based on project costs

SWPPP Plan Review (Subdivisions)  Planning Department Fees  Engineering Department Fees
1-4.99 acres  None  $1,000
5-10 acres  None  $1,500
Greater than 10 acres  None  $2,500
Yearly renewal fee  None  $300