TOWN OF HAMBURG
  6100 S. Park Ave
  Hamburg, NY 14075
  716-649-6111
  www.townofhamburgny.gov

  Schedule of Fees  January 1, 2027

SITE PLAN REVIEW FEES  Fees
Sketch Plan  $250  $250
Public Hearing  $350  $350
Preliminary Engineering Fee*  $400  None
Minor Addition and site improvements  $400  $400
Less than 1 acre  $1,000  $1,000
1 to <2 acres  $1,750  $1,750
2 to <5 acres + $500 per acre over 2  $2,000  $2,000
5 to <10 acres + $500 per acre over 5  $5,000  $5,000
10 acres & above + $500 per acre over 10  $10,000  $10,000
  $750, $1,000, $1,500, $2,000 & $2,500 $750, $1,000, $1,500, $2,000 & $2,500
Re-review of site plan materials (not a new application)
  (for each category)  (for each category)
Special Use Permit  $350 + site plan fees  Site plan fees only
Site Plan Waiver  $150  $150

SWPPP Plan Review (Site Plans)  Planning Department Fees  Engineering Department Fees
1-4.99 acres  None  $1,000
5-9.99 acres  None  $1,400
10 acres or greater  None  $1,900
Yearly renewal fee  None  $300

*Preliminary Engineering Fee is required for all site plan applications at the time of submittal to the Planning Department. A separate check made to the Town of
Hamburg is required. The amount will be deducted from Engineering Department Fees should the application move forward to engineering review following
Planning Board approval. If not, the fee shall be forefeited.

  Page 2 of 2

  60