Draft Local Law for Battery Energy Storage Systems

Government
Town of Wales
Kind
Other
Topics
Energy and data center siting, Zoning and land use, Public safety, Water, sewer and drainage, Budget and taxes, Audits and oversight, Housing

Original document

Text · page 12 of 17

Read the whole document on one page (all 17 pages, each with its own heading)

This document was a scan. Its text was produced by character recognition and may contain errors; check the original for exact wording.

Draft Wales Chapter #197 Battery Energy Storage Systems
  Initial Draft (dated 10/26/26)

  (b) Procedures for inspection and testing of associated alarms, interlocks, and controls.
  (c)  Procedures to be followed in response to notifications from the Battery Energy Storage
  Management System, when provided, that could signify potentially dangerous
  conditions, including shutting down equipment, summoning service and repair
  personnel, and providing agreed upon notification to fire department personnel for
  potentially hazardous conditions in the event of a system failure.
  (d)  Emergency procedures to be followed in case of fire, explosion, release of liquids or
  vapors, damage to critical moving parts, or other potentially dangerous conditions.
  Procedures can include sounding the alarm, notifying the fire department, evacuating
  personnel, de-energizing equipment, and controlling and extinguishing
  the fire.
  (e) Response considerations similar to a safety data sheet (SDS) that will address .
  response safety concerns and extinguishment when an SDS is notrequired.
  (f)  Procedures for dealing with battery energy storage system equipment damaged in a fire
  or other emergency event, including maintaining contact information for personnel
  qualified to safely remove damaged battery energy y storage system equipment from the
  facility.
  (g) Other procedures as determined necessary) by the Town of Wales to provide for the
  safety of occupants, neighboring properties, and emergency responders.
  (h) Procedures and schedules for conducting drilts of these procedures and for training local
  first responders on the contents of the plan and: appropriate response procedures.
1. Special Use Permit Standards.
  1.  Setbacks. Tier 2 Battery Energy Storage Systems are only permitted in Ag-Zoning districts
  and shall have a front setback no less than 300’ from the edge of the road frontage Right

  boundary lines. The rear “yard setback shall be no less than 100’ from the parcel’s rear
  boundary line. For: all situations. the site. plan shall take into account neighboring dwellings
  and/or commercial structures: which are considered by this Chapter as non-participating
  entities. The ‘distance from the-applicant’s BESS structure(s) to the nearest non-
  participating entity,on all nearby parcels shall always meet a structure-to-structure
  distance of at least a 200 feet>

  During. the Town of Wales’ s Site Plan review process, based upon unique project site
  layouts, the Planning Board advisory recommendations, and the Town Board’s action(s)
  may: require: additional setback distances for justifications related to the parcel geometry,
  néarby neighbors, conflicting land use, nearby dwellings or structures, and other relevant
  ~  factors, including, but not limited to, noise criteria. In all cases the predicted and
  - measured noise level at the parcel’s boundary lines shall meet the dB requirements of this
  Chapter.
  Height. Tier 2 Battery Energy Storage Systems shall comply with the building height
  limitations for principal structures of the underlying Ag-Zoning district.
  Fencing Requirements. Tier 2 Battery Energy Storage Systems, including all mechanical
  equipment, shall be enclosed by a 7-foot-high security fence with a self-locking gate to
  prevent unauthorized access, unless housed in a dedicated-use building with a structure
  and design so as to not interfere with ventilation or exhaust ports required for safe
  operations.

POWN  OF WALES ~ BAS