Draft Wales Chapter #197 Battery Energy Storage Systems
  Initial Draft (dated 10/26/26)

  XXxXil.  An approved energy management system shall be provided for battery
  technologies other than lead-acid and nickel cadmium for monitoring
  and balancing cell voltages, currents, and temperatures within the
  manufacturer's specifications. The system shall transmit an alarm
  signal to an approved location if potentially hazardous temperatures or
  other conditions such as short circuits, over voltage or under voltage
  are detected.
  h.  Structural Requirement Compliance:
  i.  If the battery energy storage system is wall mounted and its weight is
  more than 200 pounds, provide structural details in: the drawings and
  calculations as a separate document (Uniform Cede). ©
  il.  If multiple battery energy storage systems are:installed and the
  combined weight is 400 pounds or more, provide structural details in
  the drawings and calculations as a separate document (Uniform Code).
  2.  Utility Lines and Electrical Circuitry. All on-site utility lines shall be placed
  underground to the extent feasible and as permitted: by the. serving utility, especially
  in the case of residential or commercial sites which require’new or upgraded
  infrastructure from the serving utility. Exceptions are allowed for the main
  disconnect, if any, at the utility company. right-of-way and any new interconnection
  equipment, including without limitation any. Poles, with new easements and right-of-
  way.  one  oe  SS .

  3.  Signage. No permanent BESS signage
  s  at the rode. or in or near the roadway right
  of way is permitted, with the exception of temporary promotional advertisement for
  the project contractor during, or immediately following the site’s commissioning.
  The presence of any promotional signis. limited to 60 days after approval and
  closeout of the Town: of Wales permits.

Section 197-8:  Permitting Reauiterents for Tier 2 Battery Energy Storage Systems (> 600kWh)

Tier 2 Battery Energy: Storage systems are permitted only through the issuance of a Special
Use Permit and may. only be considered within the Agricultural (Ag) zoning district. Tier 2
BESS projects are larger, potentially Utility-Scale Systems, and shall be subjectto the Uniform
Code and the: tigorous site plan review and application requirements set forth in this Section.
Tier 2 applications via Special Use Permits, must be in full compliance with all submission
requirements before they shall. be considered a “complete application” by the reviewing
agencies in Wales.

  A  Applications for. the installation of Tier 2 Battery Energy Storage System shall be:
  4,  Reviewed by the Code Enforcement Department, the Wales Planning Board, and the
  oe  Wales Environmental Board for completeness. An application shall be deemed
  “complete when it addresses ail matters listed in this Local Law including, but not
  necessarily limited to,
  (a) Supply of a professional land survey, showing all parcels involved with the
  project with nearby adjoining parcels indicated clearing showing the location of
  buildings and dwellings on those adjoining parcels. The survey must be signed
  and sealed by a NYS licensed Professional Land Surveyor.
  (b) Compliance with all applicable provisions of the Uniform Code and all applicable
  provisions of the Energy Code confirmed by a NYS Licensed design
  professional, such as a Professional Engineer, a Registered Architect, or a

TOWN  OF WALES  ~ BATTERY  ENERGY  STORAGE  SYSTEMS