Draft Wales Chapter #197 Battery Energy Storage Systems
  Initial Draft (dated 10/26/26)

  62 days of the public hearing, which can include approval, approval with conditions, or denial.
  The 62-day period may be extended upon consent by both the Town Board and the
  Applicant.
  B.  Utility Lines and Electrical Circuitry. All on-site utility lines shall be placed underground to the
  extent feasible and as permitted by the serving utility, with the exception of the main service
  connection at the utility company right-of-way and any new interconnection equipment,
  including without limitation any poles, with new easements and right-of-way.

  C.  BESS Signage.
  1. The signage shall be in compliance with ANSI Z535 and shall include the type of technology
  associated with the battery energy storage systems, any special hazards associated, the
  type of suppression system installed in the area of battery energy-storage systems, and 24-
  hour emergency contact information, including reach-back phone: number,
  2. As required by the NEC, disconnect and other emergency shutoff information shall be clearly
  displayed on a light reflective surface. A clearly visible warning:sign concerning voltage shall
  be placed at the base of all pad-mounted transformers and ‘substations.
  D.  Lighting. Lighting of the battery energy storage systems shall be limited to that  .
  minimally required for safety and operational purposes and shall be (easonably
  shielded and downcast from abutting properties.  es  :
  E.  Vegetation and tree-cutting. Areas within. 50. feet on: each side of Tier 22 Battery Energy Storage
  Systems shall be cleared of combustible: vegetation and other combustible growth. Single
  specimens of trees, shrubbery, or cultivated ground cover such as green grass, ivy, succulents,
  or similar plants used as ground covers shall be permitted to be exempt provided that they do not
  form a means of readily transmitting fire. Removal: of trees should be minimized to the extent
  possible.  :

  F.  Noise. The 1-hour average noise generated from the battery energy storage systems,
  components, and associated ancillary equipment shall not exceed a noise level of 60 dBA as
  measured at the’ property line / boundary line of any non-participating residence or occupied
  community building adjoining. or adjacent parcel. Applicants may submit equipment and
  component manufacturers noise ratings to demonstrate compliance and a NYS Licensed
  Professional Engineer certification is supplied which indicates that the manufacturer's ratings
  are technically valid and applicable for the specific site plan of the BESS project. The applicant
  may.be required to provide Operating Sound Pressure Level measurements from a reasonable
  number of sampled locations at the parcel’s perimeter of the battery energy storage system to
  demonstrate compliance with this standard.
  9
~ G, ‘Decominissi  i
  “4.  Decommissioning Plan. The applicant shall submit a decommissioning plan, developed in
  “accordance with the Uniform Code, to be implemented upon abandonment and/or in
  conjunction with removal from the facility. The decommissioning plan shall include:
  (a) Anarrative description of the activities to be accomplished, including who will perform
  that activity and at what point in time, for complete physical removal of all battery
  energy storage system components, structures, equipment, security barriers, and
  transmission lines from the site;

  (b) Disposal of ail solid and hazardous waste in accordance with local, state, and federal waste
  disposal regulations;
  (c) The anticipated life of the battery energy storagesystem;

 TOWN  OF WALES ~ BATTERY  ENERGY  STORAGE  SYSTEMS  g