Pond and Wetland Level 1 Inspection
The Level 1 Inspection focuses on the drainage area (PW 1), inlet pipes or swales (PW 2), pond area and embankments
(PW 3) and pond outlet structures and outfall (PW 4). This inspection should be conducted on a regular basis to ensure
that a buildup of trash, vegetation, or sediment does not interfere with the pre-treatment, pond or wetland, and the outfall’s
normal flow or function. Pond embankments and dams should be regularly inspected for evidence of erosion, burrowing or
tunneling animals, and large woody vegetation growing on the dam.
PW 1. Drainage Area

Description: The drainage area conveys runoff to and is uphill from the pond inlet. When it rains, water runs off through
roof drains, yard drains, parking lots, roadways and underdrains to the ponds. Flow is through underground piping
systems, overland via swales, or across the ground as sheetflow. Sometimes, the runoff will contain dirt, grit, grass
clippings, leaves and woody debris that can collect in the drainage system. If left alone, blockages can occur and increase
the chance of shallow flooding or standing water. Standing water in drainage systems foster mosquitos, pipe corrosion,
and possible nuisance and odor conditions.
Instruction: Look for areas that are uphill from the pond. Consult Table 2.10.1 below:

  Table 2.10.1 PW Drainage Area
Problem (Check if Present)  Follow-Up Actions

    Seed and straw areas of bare soil to establish vegetation.
    Fill in eroded areas with soil, compact, seed and mulch with
  straw to establish vegetation.
    Other:

    Kick-Out to Level 2 Inspection: If a rill or small channel is
   Bare soil, erosion of the ground (rills washing out the dirt)  forming, try to redirect water flowing to this area by creating
  a small berm or adding topsoil to areas that are
  heavily compacted.
    If large areas of soil have been eroded or larger channels are
  forming, this may require rerouting of flow paths or use of an
  erosion-control seed mat or blanket to reestablish acceptable
  ground cover or anchor sod where it is practical.

    Piles of grass    Remove or cover piles of grass clippings, mulch, dirt, etc.
  clippings, mulch,   Remove excessive vegetation or woody debris that can block
  dirt, salt, or  drainage systems.
  other materials   Other:

    Open containers
  of oil, grease,   Cover or properly dispose of materials; consult your local
  paint, or other  solid waste authority for guidance on materials that may be
  substances  toxic or hazardous.
  exposed to rain
  in the drainage   Other:
  area

Maintenance Guidance  36

  Page 1025 of 1174