Text · page 414 of 1174
Read the whole document on one page (all 1174 pages, each with its own heading)
7/27/26, 8:55 AM NYSDEC eBusiness Portal System - Construction General Permit (CGP) Electronic Notice of Intent (eNOI) GP-0-25-001. Revision 1
43. SWPPP Preparer Address
300 Pearl Street
Suite 130
Buffalo, NY 14202
Download SWPPP Preparer Certification Form
Please take the following steps to prepare and upload your preparer certification form:
1) Click on the link below to download a blank certification form
2) The certified SWPPP preparer should sign this form
3) Upload the completed form
Download SWPPP Preparer Certification Form
44. Please upload the SWPPP Preparer Certification
NONE PROVIDED
Comment
NONE PROVIDED
44.a. Has the SWPPP Preparer Certification Form been signed by the SWPPP
preparer in accordance with Part VII.J of GP-0-25-001?
NONE PROVIDED
Erosion & Sediment Control Criteria
45. Has a construction sequence schedule for the planned management practices
been prepared?
Yes
Post-Construction Criteria
Site Planning and Soil Restoration
46. Identify all site planning practices that were used to prepare the final site
plan/layout for the project.
Building Footprint Reduction
Sidewalk Reduction
Preservation of Undisturbed Area
Preservation of Buffers
Reduction of Clearing and Grading
47. Indicate which of the following soil restoration criteria was used to address the
requirements in Section 5.1.6 ("Soil Restoration") of the Design Manual.
All disturbed areas will be restored in accordance with the Soil Restoration requirements in
Table 5.3 of the Design Manual (see page 5-22).
https://nform-prod.dec.ny.gov/app/#/submissionwizard/ea47aba3-47ef-4702-8e38-18fda6040ce5/12 7/10
Page 414 of 1174