Southtowns Record

TB 2026-01-07 Agenda Packet

Government
Town of Boston
Board
Town Board
Meeting
Jan 7, 2026
Posted by publisher
May 22, 2026
Kind
Agenda packet
Topics
Budget and taxes, Zoning and land use, Water, sewer and drainage, Public safety, Parks and recreation, Audits and oversight, Roads and traffic, Short-term rentals

Original document

Same meeting

Text · page 30 of 139

Read the whole document on one page (all 139 pages, each with its own heading)

ECSD No. 3 Board ctf Managers
  December 3,2025 Meeting Minutes
  Page 3 of 5

ITEM NO. 6 _ MISCELLANEOUS & INFORMATIONAL ITEMS

  a  Operational Report

  Mr. Kaminski presented the following operational report:

  Soulhtowns AIITF Expansion Project - Phase,l: Dealt with numerous operalional
  challenges during the substantial completion period ofthis project including coordination
  efforts with the Contractor conceming parking area restoration activities.

  Mr. Hojnacki presented the following collection systems report:

  Collection System Repairs: Completed a sanitary main spot repair on Amsdell Rd. in the
  Town of Hamburg in preparation for a subsequent Cured-in-Place Pipe lining project at
  this location.

  .  Milestrip Road Odor Control: Replaced all manhole carbon inserts along Milestrip Rd.,
  in the Town of Orchard Park, in response to an odor complaint.

  b.  Construction Status Report

  Contract No. 73 (Southtowns AWTF Influent Screening&olacement) - Hohl Industrial
  Services installed all equipment and completed punch list items for the general/mechanical
  contract. Closeout will be requested at the next meeting.

  Contract No. 74-C (Southtowns AWTF Exoansion Phase l) - Major building and process
  work has been completed. Portions of this project, such as the outfall cleaning and repair. are
  being issued substantia[ completion. The remainder of building and process systems should
  be completed in the next couple of months. Change Order No. 2, involving the installation of
  influent piping and facilities to expedite construction for Phase 2, will be completed in the
  spring. Site work will also be completed in the spring. Original Contract work should be
  completed by the Contract No. 74-C completion date of March 6, 2026.

  Contract No. 75 (Southtowns AWTF Expansion Phase 2) - This project is expected to bid in
  2026

  Co  n Collections Facili - The new building is fully erected with
  masonry work taking place. Concrete and pavement construction have been completed.
  Windows and doors are being installed next. Due to weather delays this past spring, the
  building delivery being delayed, and delayed steel worker availability, a 90-day time
  extension was issued making the new completion date February 16,2026.

  Contract No. 8l (South towns AWTF Exoansion Pre-Phase 2 Electrical U na rad es) - This
  project is in the shop drawing submittal and approved stage which will be followed by an
  anticipated lengthy equipment procurement timeframe. Onsite work for this project could
  start as late as2027. The scheduled Contract completion date is July 19,2028.