Engineer’s Report  December 2025

  in Appendix A.

  The proposed development will disturb approximately 0.54± acres (0.01±
  acres of total disturbance area is within Quaker Road ROW (US 20A) for
  pavement connection and restoration) and will consist of 0.31± acres of
  pervious area with 0.39± acres of impervious area. Because the proposed
  development is a redevelopment with a disturbance area less than one
  acre, only erosion and sediment control measures are required.

  Hydrographs representing pre-development and post-development runoff
  have been generated using the Soil Conservation Service-TR-55 and TR-
  20 methodology utilizing HydroCAD software. Hydrographs for the 1, 10,
  25, and 100-year storm events under existing conditions and the 1, 10, 25,
  and 100-year storm events under proposed conditions were generated and
  are included in Appendix A. The post developed discharge rates from the
  proposed stormwater conveyance system will not exceed the existing
  runoff rates for the 1-year, 10-year, 25-year, and 100-year storm events of
  the corresponding pre-development drainage area.

  The following table summarizes these pre-development and post development
  peak runoff conditions for the project site:

  Stormwater Runoff Summary

  Proposed Swale
  Pre-Development  Post Development
  High Water
  Peak Runoff Rate  Peak Runoff Rate
  Elevation (ft)
  (cfs)  (cfs)
  Top of Bank 902.00
  (Link “PRE”)  (Link “POST”)
  (Pond “SWALE”)

  1-Year  0.45  0.45  900.91
  10-Year  1.07  0.93  901.23
  25-Year  1.46  1.24  901.40
  100-Year  2.29  2.11  901.93

  3.  NYSDEC SPDES General Permit

  The proposed development will result in less than 1-acre of soil disturbance
  and therefore does not require a NYSDEC SPDES General Permit for
  Stormwater Discharges from Construction Activity, GP-0-25-001 or
  preparation of the associated Stormwater Pollution Prevention Plan
  (SWPPP). However, temporary erosion and sediment control measures
  were incorporated into the design plans.