Engineer’s Report  December 2025

  C. Stormwater Management

  1.  Existing Conditions

  The project site (0.70± acres) currently contains an 1,860± ft² commercial
  building, 11 parking spaces, and grass/wooded area surrounding the
  building and parking area. The topography of the project site is sloped
  towards Quaker Road (US 20A). Stormwater generally flows to the
  existing storm sewer system or to the south of the site. The project site
  consists of 0.57± acres of pervious area and 0.14± acres of impervious
  area (0.01± acres within the Quaker Road ROW (US 20A)).

  According to the New York State Department of Environmental
  Conservation (NYSDEC) Environmental Resource Mapper, no portion of
  the project site contains any state regulated or federal wetlands. See
  Exhibit 2 – NYSDEC Environmental Resource Mapper.

  The Federal Insurance Rate Maps (FIRM) for the Town of Aurora, Erie
  County, New York prepared by the Federal Emergency Management
  Agency Community Panel No. FM36029C0369H dated June 7th, 2019,
  indicates that the proposed project site contains no area within the 100-
  year floodplain. See Exhibit 3 – FEMA Firmette.

  Based on the USDA Web Soil Survey, the site is considered to contain
  97% Niagara silt loam (NfA) and 3% Canandaigua silt loam (Cc). It is
  assumed that this soil type has a hydraulic classification of “C/D” and the
  site is described as 100% poorly drained soil (See Exhibit 4 – Site Soil
  Map).

  2.  Post Developed Conditions

  The post developed watershed boundary includes the same total
  drainage area as the pre-developed watershed. The stormwater from the
  proposed building and parking area will be conveyed to the new catch
  basins within the proposed parking area which drains to the NYSDOT
  existing catch basin within the Quaker Road ROW (US 20A). Within the
  proposed stormwater conveyance system, a two (2) foot deep flat bottom
  swale is proposed to mitigate some of the stormwater runoff from a
  portion of the building and the southern parking area. The catch basins
  within the southern parking area and most of the building’s roof leaders
  are tributary to the proposed swale which will detain a portion of the runoff
  prior to discharging the excess stormwater into the northern part of the
  proposed stormwater conveyance system which ultimately discharges
  into the existing stormwater conveyance system within Quaker Road (US
  20A). The proposed swale daylights the stormwater runoff and creates a
  delay in the peak runoff from the southern portion entering the northern
  portion of the proposed stormwater conveyance system. This delay
  allows for the existing storm sewers within Quaker Road (US 20A) to
  contain a lesser flow rate during the peaks of the storm events reducing
  the probability of flooding. The watershed delineation maps can be found

Greenman-Pedersen, Inc.  GPI No. WNY-2500056.00  Page 6